Piping MTO & Bulk Material Estimation: How Quantities Are Extracted from 3D Plant Models

Lead Material Control Engineer
Engineering Operations, Deep Ocean
Published: 2026-06-20•9 min read
Piping material bill of quantities report and 3D plant CAD model review
Governing Standards:ASME B16.5ASME B16.9PIP PNE00001

Key Engineering Takeaways

MTO 1 (Preliminary, 30% stage) provides order-of-magnitude quantities for mill reservation of long-lead exotic pipe and heavy wall forgings.
MTO 2 (Intermediate, 60% stage) commits 80–90% of bulk procurement, incorporating realistic scrap and cut-length wastage factors.
MTO 3 (Final, 90–100% stage) is directly derived from frozen IFC isometrics, reconciling shop spools against field weld allowances.
Catalog data integrity in AVEVA E3D / SP3D is critical; mismatched component descriptions cause major procurement purchasing errors.

1. The 3 Milestones of EPC Piping Material Take-Off

Managing piping procurement requires staged MTO releases aligned with project financial commitments: - **Preliminary MTO (MTO 1 - 30% Engineering):** Extracted from preliminary 3D routing and plot plans. Used to purchase long-lead items (LLIs) such as alloy pipes, heavy wall fittings, large-bore valves (NPS 16+), and special metallurgy items with 6–10 month mill lead times. - **Intermediate MTO (MTO 2 - 60% Engineering):** Extracted after major equipment nozzles, rack headers, and valve stations are placed. Used to commit approximately 85% of total bulk materials (carbon steel pipe, standard tees, elbows, flanges, and gaskets). - **Final MTO (MTO 3 - 90% Freeze / IFC Release):** 100% reconciliation against Issued-For-Construction isometrics. Identifies minor balance-of-material buyouts and field-route tie-ins.

2. Applying Engineering Scrap & Wastage Allowances

Bulk pipe cannot be ordered purely on net centerline length extracted from the 3D model. Scrap and cut allowances must be applied: - **Straight Pipe (NPS 2 and above):** Add $5\%$ to $8\%$ contingency for cutting wastage, beveling offcuts, and field route adjustments. - **Small-Bore Pipe (NPS 1.5 and below):** Add $10\%$ to $15\%$ contingency due to on-site field routing around structural obstacles. - **Fittings & Flanges:** Add $3\%$ to $5\%$ contingency for fabrication shop scrap and hydrotest blanks. - **Bolts, Studs & Gaskets:** Add $10\%$ contingency for field losses, torque check replacements, and hydrotest gasket changeouts.

3. Special Piping Items (SP Items) & Inline Instrumentation

Specialty items must be tagged independently in the MTO database: - Inline instruments (orifice plates, magnetic flowmeters, control valves) are purchased by the instrumentation discipline; piping MTO extracts only mating counter-flanges, studs, and gaskets. - Specialty piping components (temporary strainers, spectacle blinds, flame arrestors, steam traps, flexible hoses) require distinct engineering requisition numbers linked back to P&ID tags.

Related Engineering Services & Execution Track Record

Procurement Accuracy

Need Audit-Proof Piping Material Take-Offs Extracted from Your 3D Model?

Deep Ocean extracts clean, itemized MTO databases with automated component validation to prevent procurement shortfalls.

Request Callback